Menu:   business cases / project support / 

Business case history “Project support”

For an engineering office with 15 employees, Prime Office adapted and simplified the IT infrastructure to meet the needs of new circumstances. At the same time, the existing IT problems were addressed and resolved by experienced IT experts from Prime Office.

 

Example of a completed project:

Engineering office in construction and related trades

Employees

15

IT employees

 

none, multiple power users

IT systems

organically developed and complex infrastructure, collection of various applications and systems; a total of 12 servers, multiple networks, Internet connections and VPN (remote access)

Problems

everything was running adequately well, but changes and expansions were very difficult to implement

Project goal

consolidation of all systems and the infrastructure

Time frame

planning and implementation over a period of 4 months

Work carried out

  • Develop project plan and cost estimates
  • Virtualization of the physical server based on VMware vSphere 4
  • Simplify the system environment and interfaces
  • Create system documentation

Simplification of the IT infrastructure

The virtualization of the exis­ting IT infrastructure lowers costs, simplifies system maintenance while guaran­teeing the improved availa­bility and reliability of all systems and applications.